Concrete Construction - Introduction to Slab on Grade Construction
Don't forget to bookmark this site and share it with your friends!
Subgrade Preparation
The key to a quality slab starts from the bottom up.
The first thing you must do is make sure all the topsoil is removed, this is layer of soil is where the grass grows and it is full of organic material. It can vary in depth from a couple of inches to well over a foot, depending on what part of the country you live in.Once you have removed all of the topsoil you want to use a plate tamper or roller (for a large area) to make sure the subgrade is highly compacted. By compacting the soil you are minimizing the chance that the soil will move in the future, and that is a source of cracking known as movement cracks or heaving.
This is also the time you want to make sure the subgrade is far enough below the eventual floor this is known as subgrade elevation and contour. For example, if you are planning on putting down four inches of concrete over four inches of stone, the subgrade should be at a fairly level 8 inches below where the eventual floor will be. If an excavating company is doing the work, specifications usually require them to be within 2/10ths of a foot (+/-), that's about 2 1/2 inches either way, but most good contractors using laser leveling equipment will be within 1/10th of a foot (better than 1 1/2 inches) of the desired grade.
This is also when plumbing and electrical rough-ins and anything else that needs to come up through the concrete is placed in the soil. It is extremely important that these items are backfilled and compacted as they are installed. Placement of concrete over poorly compacted pipe runs will almost surely end up cracking as the soil settles because it will create a stress point for the concrete. It is not recommended that these pipes be placed above the base as it will act as a "reverse" sawcut and will assuredly crack along the pipes path.
Stone Grading & Vapor Barrier
Once the subgrade is compacted, you can place stone to act as a cushion and to help keep water from migrating up through the slab. I recommend 3/4 - 1" stone because you don't have to compact it after it is spread. If you use a smaller stone, sand, caliche, or similar base material, you will have to use a mechanical method of compaction such as a jumping jack, vibratory plate, or roller to compact the material to approximately 95% compaction. Use a laser or string-line when you are spreading it to maintain grade. To ensure correct concrete depth you can use rakes and shovels to smooth out the stone/aggregate. This is known as fine grading and when you are done the base should be within 1/4" at any given spot.After the stone is graded the vapor retarder or vapor barrier is installed. Please note that there is a distinct difference between vapor retarders and vapor barriers. Vapor Retarders are most common and are used to create a membrane barrier between the concrete and the ground to minimize the concrete's ability to "wick" moisture up through the concrete. Vapor Barriers are designed to eliminate ground moisture and generally are only used in areas with high ground water, poor ground percolation, highly acidic or alkaline soils, and "clean room" applications.
For most applications polyethylene (plastic) sheeting is adequate as a vapor retarder. It is available in various dimensions and thicknesses (mils). Common thicknesses that are used for Slab-on-Grade (SOG) construction are 4, 6, and 10 mil. The thicker the poly the stronger it is but don't automatically grab the 10-mil poly, it is generally only used for the heaviest applications. Generally as a rule of thumb 4-mil is used for residential, 6-mil is used for light to medium commercial and 10-mil is used for heavy commercial and industrial applications. To get the best results from the vapor retarder, the joints or seams should overlap at least 6" to 12". After lapping the joints they should be taped to prevent water seepage.
When the specifications require a more robust vapor barrier they will call out a specific product or product family. Examples of vapor barriers include StegoWrap by Stego Industries and Flopruf by Grace Construction Products.
Books on Concrete Construction
Forming the Edges of the Slab
Now that the stone is down, use 2x4's or whatever lumber you need to get the concrete thickness you are looking for. Every four or five feet you want to brace the form so that the pressure from the concrete doesn't push the boards over. This edge form serves two purposes, it holds the concrete in, and acts as a guide for placing and finishing. Because it is acting as a guide, you want these edge form boards to be very level. Use a string-line and level to make sure they are level and plumb, I can not overemphasize this step, check it, then recheck it and just before you place the concrete - check it again!
Slab Reinforcing
After the edges are formed, there are three popular methods of reinforcing the slab, they are reinforcing steel (rebar), welded wire mesh (WWF) and fibre. Rebar is generally not needed for a light duty slab, but if you are planning on having heavy items sit on the slab for a long time or will have heavy vehicles on the slab (driveway?) you will want to use at least #4 rebar placed every 12" or so in each direction.For a lighter duty slab you can opt for welded wire fabric which comes in various guages (wire diameter) and spacing, typically we use 1.4 or 2.1 6x6 WWF for most medium duty slabs.
The third option is fibre mesh, which is installed at the concrete plant. It is composed of thousands of tiny fibers that are suspended in the concrete and take the place of WWF, it is not recommended to substitute fibre for rebar, but if added to the mix it can give added strength to the concrete. The biggest drawback with fibre is that sometimes after finishing there will be tiny hair-like fibers protruding through the concrete. These protruding fibres can be burnt off with a propane torch, or just left - they will eventually rub off. Though fibres are still a bit controversial they are gaining acceptance in various circles. If you go with the fibre, you definetly want the approval of the owner and input from both the structural engineer and concrete mix designer before proceeding.
Placing and Finishing the Concrete
Check to make sure everything is ready before the concrete arrives, the equipment should have all been started to make sure it is running and everything should be in good repair.
Did you remember:
Subgrade Compaction?
Plumbing Rough-In?
Electric Rough-In?
Embedments?
Stone?
Vapor Barrier?
Edge Forms/Box-outs?
Hand tools (Concrete rakes, bull float, edgers, floats, knee boards, hand trowels, etc.)?
Power tools (trowel machine, vibrator, georgia buggy, etc.)?
Ok, so start by placing the concrete and raking it level, this will take a couple of people, behind the placers someone will be vibrating the concrete and "striking off" the concrete to knock down any high spots.
After the concrete is leveled off, a bullfloat is floated accross the top to make everything semi smooth.
Once the concrete has been floated off, the edges are started with an edger tool and hand floats while the concrete is "setting up" (starting to get hard).
After the concrete can support the weight of a person the trowel machine is used to repeatedly trowel off and smooth the top of the concrete until it reaches the desired finish - this is called "burning in" the concrete.
Curing the Concrete
Regardless of the method used for curing, you should let the slab "cure" for at least 7 days before you use it. Concrete never completely cures, the hydration process continues for years, but by 7 days it should be between 75-80% of design strength.
Thanks for your support!
Handy Links
- How To Build High Quality Slabs on Grade - The Concrete Network
- Reasons for building a slab on grade, tips for proper subgrade compaction, types of foundations, curing info, and more.
- Concrete Technology and Construction | Focus on Concrete Floors | Portland Cement Association (PCA)
- Resources and educational material on cement and concrete technology.
- T-shirts, mugs, and decals to support this article
- T-shirts, mugs, bumper stickers, and decals that help support this and other lenses.
- Follow this link if you like this website and would like to do your own
- If you like what I've done here and think you might want to give it a shot, it is really easy and doesn't cost anything, just follow this link!
Slab on Grade Feedback
What do you think?
I would appreciate your feedback about my little how-to on concrete slabs on grade. Thanks!
-
Reply
- stargazer00 stargazer00 Oct 5, 2009 @ 7:40 pm
- Congratulations on the new Giant badge!
-
Reply
- chris chris Jul 15, 2009 @ 11:31 pm
- Placing concrete directly on plastic sheeting is not recommended anymore. Placing the sheeting on subgrade, and gravel over the sheeting aids proper concrete curing, and reduces slab curl.
-
Reply
- Rajays Rajays Apr 24, 2009 @ 12:35 pm
- A SquidAngel Blessing for this lens. I learnt something new here today! :)
I would like to invite you to join the Giant Squidoo Challenge 2009. You have created some good lenses and I believe you are a Giant Squid material. Learn more about the challenge and the teams at http://www.squidoo.com/rajays-rocking-squids Hope you will join the competition and our team.
-
Reply
- LC LC Mar 1, 2009 @ 4:09 pm
- Very helpful. Thank you!
-
Reply
- Alan C. Alan C. Feb 11, 2009 @ 12:37 am
- a nice lesson to refresh my memory.
*You'd want to pour straight through. Pouring the footings first then the slab will cause a cold joint, which is weak and generally avoided. Formwork is quite easy for a 1 story building, just take a look at any general construction project.
- Load More






















